Does anyone have the picture that goes along with this step?
82. At this point the Super charger is installed and it’s time to bolt the brackets together. The blower already has the main bracket on the blower and the pulley will already be installed on the blower. The pulley has been removed for better picture clarity.
Be sure bolt “B” is installed in the main bracket loosely. Swing the alt up to connect with mounting point “E”. Loosely install a the 40mm M8 bolt at point “E”. Loosely install the 40mm M8 bolt and nut at point “A” to the support bar as shown. Loosely install the bolts at point “C” and “D”—USE BLUE LOCTITE ON POINTS “C” AND “D”. You may need to rotate the main bracket a bit for everything to line up. Once the bracket are all lined up and ALL bolts have been loosely installed, tighten the bolts in this order:
E, D, C, A, B.
Torque specs for the above are as follows:
A and E, 15ft/lbs
C and D, 30 ft/lbs
B, 10 ft/lbs
Thanks,
Todd
__________________
Current: 2005 Elise LRG - BWR SC
Gone, but not forgotten: '91 NSX, '95 Z3, '79 280ZX, '66 Mustang and others. Friends don't let friend's drive 4-doors.
|