As many that read my posts can surmise I'm a hands on guy. I an fortunate to have the knowledge, skills and tools to perform most jobs and mods.One thing that I think would be helpful to people using this board is real times for DIY jobs and mods. I define a real-time for a job as the time that elapses between pulling your lotus into the garage to pulling it out with the job completed. I think some posts may state an artificially short time for a install not including the time to take off wheels , pans ect. This came to mind when I installed the force fed damper( see post). We could make this a sticky for true DIY times I'll start.

Install Nitrons includes lifting or jacking,R&R wheels and top front shock mounts 2-2 1/2hrs note does not include setting ride height corner balance or alignment add 3-4hrs(trust me i've done this many times)

Force fed damper 1 1/2hrs add 1/2hs for RTD brace.

Oil and filter 1hr

Change front brake pads 3/4hr, remember all times include jacking and R&R wheels.

Change rear pads 1 1/4 hrs.

Change springs on Nitrons or Olnins 3-4hr includes resetting corner bal and ride height check alignment but no adjustment.

Install Sector 111 RTD brace and reset rear toe and thrust angle 3-3 1/2hrs.

This is a start. carl